Cameron House

Scotland

Project Summary

Following a visit to our factory in Ireland, Paul Hopkinson, manager at Cameron House Marina in Loch Lomond, was so impressed with the quality of our products and installation capabilities he awarded us the tender to replace the marina’s A and B pontoons.

Client Cameron House Marina
Date Installed August 2016
Where Cameron House Marina, Loch Lomond, Scotland

At 30 years old, the existing berths were no longer fit for purpose. We installed our standard leisure pontoons with the heavier GRC (Glass Reinforced Concrete) pontoon decking, giving the marina’s customers 200 non-slip, stable and sustainable berthing to enjoy their boats from.

To connect the existing breakwater to the shore, we added a new section of concrete breakwater with a bridge to make it accessible. This upgrade also incorporated the supply of new jet ski docks.

With new chain moorings and improved electrical and water service bollards Cameron House Marina is now set to provide safe and secure water access for many years to come.

“We would like to thank you and your team for their professionalism in providing an excellent product. All boat owners are happy with the new pontoons and have commented on the difference in stability compared to the old pontoons you removed. The concrete decking planks look great and even in the rain have good non-slip properties. We will be in touch for any further developments at Cameron House."
— Paul Hopkinson, Marina Manager.